Wednesday, September 03, 2008
Primer and Paint
Tuesday, September 02, 2008
Building and Installing the Floor
We also decided to keep this as a floating floor. We think that we might need to pull up the floor from time to time. If we attached it, we run the risk of cracking the concrete floor, and eliminate the ability to clean under the wood.
I started out by laying runners and then cutting the planks to the proper length. After a dry fit, the planks were screwed into the runners from the underside. The finished section was then turned over and lowered into place. The first section is five feet in length.
The second section was prepared in the same manner. The last plank of the first section was set so the runners of the second section lock into place by sliding underneath the first section. The second section measures slightly less than five feet.
The third section is slightly longer then three feet. It simply sits on top of the second section. I do not have a way to lock this section into place without driving some screws into the runners of the second section. I hesitate to use screws, as these would be visible. If we feel that it is necessary to secure this section into place, I will go back and screw it down.
I built caps at the front door and at the doorway the leads to the hallway. This has helped with the movement of the last section. These two caps are not part of the section; they are individual pieces that fit under and against the section.
The next step in this project is to paint the floor. We will need to prime it first and then cover it with a tough finish.
Friday, August 22, 2008
Painting the Porch
Thanks for the Help BLH!
Sunday, August 10, 2008
Cleaning out the Porch
Once the items are removed from the area, CMV and AMV are going to paint the walls and ceiling. Our plan is to install a wooden floor that can be removed in sections if the need arises. I am unsure how dry the area stays in the winter. It has been a bare concrete floor for so long, that I don't know how the elements will treat the wood. We are going to use a pine plank and then paint it to resemble an old porch floor.
The only picture I have is of the porch almost cleaned out. You can see the futon frame and some trim against the wall.
Friday, July 25, 2008
On the Level
There is not a spot in this house that is level. The tiles do not lay flat, and this is the main cause of them popping up. I bought 3 50 pound bags of self-leveling floor cement. It was our hope that we could pour the mixture and end up with a floor that could be tiled.
The floor had a high spot close to the middle, and it ran higher on the left side. We poured two bags of the cement and got the floor to about the highest point that we could. We did not want to get to the point of stepping down into the bedrooms.
The floor is a lot closer to level, but not quite there. We will attempt to lay the tile soon.
Tuesday, July 08, 2008
Mother Nature Finally Cooperates
Next week I will go up and apply some roof cement to some of the shingles around the vents and near the chimney. I will also apply the cement to the outer edge of the shingles on the roof line, to give them some additional holding power against the prevailing wind off of the lake. I may touch up the paint on the chimney, as it still shows some light spots, especially as the sun hits it.
Monday, June 30, 2008
Closing Out The Weekend
To add additional issues, we plugged in the air compressor, and could not get it to hold pressure. It would build to almost 20 pounds, and not move from there. There was no chance that the Coil nailer would work with that low pressure, so all of the shingles would be attached the old fashioned way, a hammer and nails.
We did get a decent block of dry time at the end of the day. During this break in the rain, CMV made decent progress tearing off shingles from the back of the house, and I nearly finished applying shingles to the front gable.
I placed the chimney down and attached it to the roof. We used the ice and water shield as added protection around the flashing. Looking at the paint job out in the sunlight shows that I need to do some touch up work on the next calm day. We were able to run the shingles up to just short of the roof line. I need to clear out more of the ridge so I can apply one run of felt across the top of the ridge and fold it over to the other side.
I am not happy using this as the end of the weekend shot, because of a couple of items. One, there is a piece of plywood nailed as a spacer where the fascia board will eventually attach. There are a few shingles that hang over the edge of the roof, that should have been trimmed. Lastly, the extra shingle should have been cut out of the metal valley.
We did a lot of work in a short amount of time today, and pushed it until the very end. I really should have put the hammer and nails away 15 minutes earlier than I did, because the rain almost caught us unprepared. We had the tarps on the house, but I had been pulling shingles out of the "weight" packs to use to finish the gable, so when the wind started blowing, the tarps didn't have enough to hold them down properly. I had to bring up another 5 bundles of shingles to use as weight. I should use that as a life lesson, because those bundles seem much heavier at the end of the weekend than they do at the start of the weekend.
Roof (Weekend #3)
I drove up on Friday morning and got started around noon. My list of priorities was to remove the shingles on the south side of the house, install the drip edge, lay out the roofing felt, apply the starter strip and start laying shingles if time allowed. I folded back the tarp and started removing the three layers of old roof. I was able to work for 2 1/2 hours and then had to cover up for a rain storm. I lost about 2 1/2 hours because of the rain.
After the storm, I was able to climb back up and fold back the tarp and work another 2 1/2 hours. In my 5 hours of working, I was able to get down to the roofing deck, and install the drip edge. I applied the starter strip and covered up for the evening. As I was standing in the livingroom, I realized that I applied the starter strip before I put on the roofing felt. I would need to pull up the strip and apply the felt first thing in the morning.
Saturday, June 28, 2008
It rained quite a bit over night. CMV arrived to find overcast skies and the threat of rain. After a brief shower, we were able to get up on the roof and get started. I removed the starter strip and applied the roofing felt. I the re-applied the starter strip, and attached drip edge on the rake edge. We were ready to shingle.
With the aid of the air compressor and coil nailer, we managed to work our way up the roof close to the top. We attached shingles upto the chimney cutout and stopped for the day. We did not have any more rain, but we had several scares. We have learned to keep the tarps at the ready.
Tuesday, June 24, 2008
The Roof (second weekend)
We drove up to the cottage (CMV, AMV & JMV) Friday night. We wanted to be there to get an early start on Saturday morning. Those of you who know me know that I am definitely a morning person, so you can understand that I was really motivated to get up on the roof first thing. I am not sure of the time when we actually got started, and CMV has not started editing my posts, so it was early.
The weather was not very cooperative this weekend. We had two different rain delays on Saturday and another two on Sunday.
We continued by removing the shingles from the front gable down to the valley. We then cleared the first four feet above the gutters, so I could replace some additional boards on the roof.
With the shingles cleared, we had enough room to prepare the valley for new shingles. We decided to lay down an ice and water shield in the valley and the attach some aluminum flashing. We applied the felt paper to the gable, and will do the same to the adjoining roof next week when all of the shingles are removed.
Tuesday, June 17, 2008
Roof (First Weekend)
The plan was to tear off the balance of the eastern facing roof and replace the bad wood. The bad wood runs the entire length of the house from front to back. It is the area where the carport attaches to the house. I would guess that someone walked on the valley and cracked the shingles, which allowed water to reach the planking.
The rotten wood was all on the carport side of the roof, which was a very good thing. When I say that, I mean that any water that leaked through the damaged area would drip to the floor of the carport. The only exception was the storage shed.
With the damaged area removed and replaced, it was time to start the tearing-off the shingles on the house. It went rather well, considering the temperature and the fact that we had a few rain scares.
We had been planning to load the trash into the back of the truck and drive to the landfill for disposal. The charge for roofing scrap is $54.95 a truckload. One charge for as much or as little as you care to load. CMV bought some construction trash bags, and started loading up the bags. We soon learned how much trash we were going to have to haul. We estimated that we would need to take four trips to the landfill @ $54.95 and that does not include the gas for the trips. CMV decided to check the availability of a small dumpster. We were not sure if they would be able to maneuver anything down the lane due to the large trees and the narrow lane.
I want to post that CMV did a fantastic job of bagging all of the roof scrap. Nice job!!
Monday, June 16, 2008
We are not too busy, why not tackle the roof 6/11-6/13
One of the problems that we noticed when we say the house for the first time, was a section of rotten wood in the carport where it meets the house. We decided to use our economic stimulis money and replace the roof.
We had a couple of companies come out and give an estimate. Two estimates of $3,000-3,500 later, coupled with the fact that I hate to pay for labor, we decided to do the job ourselves (come on, you did see that coming right?).
We purchased the materials, and I scheduled some vacation time. I took Wednesday, Thursday and Friday, June 11-13, off and planned to get quite a bit accomplished. The first task was to tear off the roof over the carport. Since I was at the cottage by myself, I knew that I could only removed as much roof as I could cover in case of bad weather.
I got started around noon on Wednesday and after a couple of hours, I had most of the old shingles off of the carport. I was finally able to see the extent of the rotten wood. It was slightly worse than I had anticipated, but still manageable. I started to remove the roofing nails and the staples when the planks started to crack lenghtwise.
I decided to replace the boards with plywood sheets to reinforce the carport. We want a nice roof that will last a long time, and I wasn't willing to risk the carport cracking apart.
I drove to Goshen, IN and purchased the plywwod sheets and some additional nails. I tore out the planks roof and replaced them with the plywood. I am actually comfortable walking on the surface, now that it is solid.
Monday, May 19, 2008
Trim
One of the projects that should have been completed long ago is re-hanging the trim around the windows and doors. It will probably not surprise you to learn that this simple task has been plagued with problems.
When we tore out all of the walls, we also removed a 3/4 inch layer of fiberboard insulation. We added the roll insulation, and hung the drywall without giving it a second thought. That was our first mistake (thank you for not going back through all of the posts and totalling the actual number of mistakes). When replaced, the trim floats 3/4 of an inch off the wall.
We tried to come up with a solution that would maintain the same look throughout the house. We figured we could add a piece of wood behind the trim, but I didn't like the thought of 1 1/2 inch trim on every window.
We quickly dismissed the idea of hanging the trim on the outside of the window frame, due to the fact that the angles and lengths would not match up.
We thought about routing out a channel in the back of the trim, but the original trim is 3/4 inch. We would have to route almost the entire thickness of the board, leaving a very thin piece of trim.
We thought about using an electric planer on the window frames and removing the extra material, but the aged wood started to split in the corners.
We ended up using a chisel and cutting out the corners of the window frame. Once the corners were ready, we used the router to remove the excess material. The only modification we will need to make is on a small piece of inner window trim. Previously, it attached to the window frame, but now it will attach to the edge of the trim.
We still need to final sand and polyurithane the trim, but it is very close to completion. We seem to have quite a few projects that are close to completion. We need to get them finished and off the to-do list.
Thursday, January 10, 2008
Checking up during winter
We made a day trip up to check on the cottage today. It is a pretty nice day, but has been very cold the last few days. The lake is still frozen, and there were several ice fishermen out. If the ice is considered safe today, it will not be tomorrow.
The place is fine. The only surprise was that the propane tank vanished. I thought that someone had taken it for their own use. It turns out that the free tank is only free if you fill it at least once a year. We have had the place for almost a year and a half, and we are still using the propane the previous owners purchased. The gas company had come by the place and picked up the tank and kindly refunded the previous owners for the gas.
We have been discussing different options for heating, as neither of us like the propane. I guess this is a sign that we need to make a decision.
I have not updated as often as I would like, so I will catch you up on our progress that we made to this point.
The drywall is finished and painted. We will need to do some touch up painting once we install the baseboards and the ceiling trim.
The flooring is complete in the living room, and both bedrooms. We need to lay the tile in the kitchen and hallway. This will be one of the first projects this spring or early summer when the weather warms up.
We need to install a new source of heat. We are leaning towards baseboards, but have not made a final decision.